Avaya lab relocation

Avaya lab relocation

Avaya lab relocation

This project involved a fast-track relocation, tenant renovation and downsizing of lab operations into a 101,593-square-foot facility in four months. Duro Electric installed all new switchboards, panel boards, lighting, controls and cable tray, as well as some specially prefabricated wiring devices. Project scope also involved the relocation of the existing UPS systems from the tenant’s previous location.

Owner | Avaya
Architect | DLR Group
Engineer | BCER
General contractor | Swinerton Builders
Contract value | $4,440,741